![](/public/uploads/images/RAH_Heliport_004/1658939172-600h_RAH_Heliport_004.jpg)
![](/public/uploads/images/RAH_Heliport_001/1658939172-600h_RAH_Heliport_001.jpg)
![](/public/uploads/images/May14,2012_007/1658939172-600h_May14,2012_007.jpg)
![](/public/uploads/images/May14,2012_006/1658939172-600h_May14,2012_006.jpg)
![](/public/uploads/images/June_5,_2012_005/1658939173-600h_June_5,_2012_005.jpg)
![](/public/uploads/images/June_5,_2012_008/1658939173-600h_June_5,_2012_008.jpg)
![](/public/uploads/images/June_5,_2012_017/1658939173-600h_June_5,_2012_017.jpg)
Location
Edmonton, AB
MARKET
SIZE
5,000 square feet
Completion
2015
Value
$4,500,000
PROJECT HIGHLIGHTS
- Foam fire suppression system
- Extensive in-slab glycol snow melt system
- Adjacent facilities remained active throughout construction
Demolition of the existing concrete helipad structure on the top of the 8-storey Northeast Parkade at the Royal Alexandra Hospital and construction of a new, concrete-and-steel helipad structure. The scope of the project included extensive architectural, mechanical, electrical, and structural upgrades to the existing structure, and tie-in of services to existing hospital infrastructure.